2012 Pavement Management Plan Roadwork List (Tentative Roadwork Schedule)

STREET FROM TO LENGTH/SQ YDS ACTIVITY DATE
A St Walcott St Cedar St 424 ft Crackseal  
B St Walcott St Cedar St 476 ft Crackseal  
Cedar St Ext Cordaville St 1400' W of Cordaville St 1388 ft Crackseal  
Daniel Shays Rd Saddle Hill Rd (S) Saddle Hill Rd (N) 2427 ft Crackseal  
Donna Pass Jamie Ln Cul-De-Sac 1886 ft Crackseal  
Hillcrest Dr Hayward St Hillcrest Dr 2203 ft Crackseal  
Huckleberry Rd 1600' S of Fruit St (W) 2100' S of Fruit St (E) 2730 ft Crackseal  
Jamie Ln Pond St Donna Pass 827 ft Crackseal  
Old Farm Rd Queen Anne Rd 900' W of Queen Ann Rd 864 ft Crackseal  
Rocky Woods Rd Wood St Rocky Woods Rd 3932 ft Crackseal  
Roosevelt Ln Fruit St Roosevelt Ln 2675 ft Crackseal  
Rough Rider Rd Roosevelt Rd Bullmoose Run 765 ft Crackseal  
Saddle Hill Rd  900' N of Clydesdale Ln 750' S of Equestrian Dr 450 ft Crackseal  
Stewart St Pond St Donna Pass 1749 ft Crackseal  
Victory Ln Cunningham Rd Fruit St 1189 ft Crackseal  
Wellington Way Chadwick Way Cul-De-Sac 513 ft Crackseal  
Wescott Dr Pond St (N) 750' of Pond St (S) 2095 ft Crackseal  
West Elm St 1100' N of West Main St 350' E of Pond St 917 ft Crackseal  
White St Cunningham Rd Wood St 707 ft Crackseal  
           
Cedar St Ext 1400' W of Cordaville Rd Southboro town line 1920 ft/4480 sq yds Reclaim  
Church Pl Hayden Rowe St Church St 285 ft/1080 sq yds Reclaim  
Walcott St Main St C St 1240 ft/ 3170 sq yds Reclaim  
           
Chestnut St 300' E of McKay St 530' E of Smith Rd 750 ft/2750 sq yds 1-1/2" Mill & overlay   
Church St Maple St Main St 1574 ft/4375 sq yds 1-1/2" Mill & overlay  
Grove St Main St 600' N of Hayden Rowe St 2865 ft/8915 sq yds 1-1/2" Mill & overlay  
Hayden Rowe St Chestnut St 90' S of College St 4000ft/12000 sqyds 1-1/2" Mill & overlay  
           
Spring St Pond St Upton town line   Repair/Replace culverts  